Renovation approvals in North York

Plan a North York home or condo renovation around Toronto permit triggers and the condo corporation requirements that affect a multi-room job.

Which authority applies to the address

North York is part of the City of Toronto, and Toronto Building is the municipal starting point for a renovation here.

The City's archives record North York joining the amalgamated city on January 1, 1998.

A multi-room project needs a description of the proposed changes before its permit requirements can be checked.

The number of rooms alone does not decide the answer.

Replacing finishes across a unit is different from changing room sizes, moving plumbing or creating another dwelling.

Send the room list and any drawings before changes, work and dates are agreed.

Source: City of Toronto Archives, former municipalities

Wall openings and room changes

Toronto lists adding or removing walls as structural or material alterations that require a building permit.

Its examples include changing room sizes or uses, so an opening between the kitchen and living room belongs in the permit check.

The wall has to be checked for supports, pipes and wiring before it is changed.

The planned opening also leaves work at the ceiling, floor and adjoining walls that needs to be measured.

Describe the opening you want and whether an existing door is moving.

MRG treats structural or specialist work as separately assessed work, and the quote should say which parts are included.

Keep the drawings and approval status with the finish choices so ordering does not get ahead of the room plan.

Source: Toronto Building, work that needs a permit

Plumbing changes and basement use

Toronto lists installing or modifying plumbing systems as permit work, while repairing or replacing plumbing fixtures appears on its list of work that does not need a building permit.

Moving a kitchen sink across the room changes the plumbing work that needs to be assessed.

Tell us where the fixtures are now and where you want them to be.

Basement plans need the same care because the City's permit list includes specified structural changes, heating or plumbing changes and adding a second suite.

A request for an office and family room should say whether the basement will remain part of the existing home.

A separate dwelling needs its own assessment before finishes or a completion date are agreed.

The City says its examples are not exhaustive, so unresolved details should go to Toronto Building for the specific property.

Source: Toronto Building, work that needs a permit

Condo approval and municipal permits

The Condominium Authority of Ontario says unit owners generally need to request board approval for renovations and may also need municipal approval.

The corporation's declaration, by-laws and rules establish what is allowed in that building.

Send the renovation application requirements with your room list, including any supporting documents management requests.

A whole-unit scope can touch several building concerns at once, including flooring, plumbing connections and work near shared walls.

Ask for the requirements that apply to those changes before the materials are ordered.

The CAO says some corporations restrict contractor hours, so a building's usable workday can be shorter than the municipal construction window.

Record the approved hours and access conditions with the planned work so they can be reflected in the schedule.

Source: Condominium Authority of Ontario, condo renovations

What the written scope needs to distinguish

Cabinet installation appears on Toronto's list of work that does not require a building permit, but other work in the same kitchen can still require one.

The scope should distinguish cabinet and finish replacement from a wall opening or plumbing change.

Mark work that still needs an assessment so its requirements can be settled before a start date is agreed.

Include drawings already prepared, approvals already received and decisions still pending in the request.

For a condo, attach the conditions management gave you when arranging the next stage of the quote.

MRG sets the work and timing in writing after those details and material availability are considered.

This keeps the room list, the permission to do the work and the finish orders tied to the same proposed renovation.

Source: Toronto Building, work that needs a permit

Questions about renovation approvals

Which authorities can affect a North York unit renovation?

North York is part of the City of Toronto, and Toronto Building is the municipal starting point for a renovation here.

The City's archives record North York joining the amalgamated city on January 1, 1998.

A multi-room project needs a description of the proposed changes before its permit requirements can be checked.

Source: City of Toronto Archives, former municipalities

What wall and room changes need a Toronto permit check?

Toronto lists adding or removing walls as structural or material alterations that require a building permit.

Its examples include changing room sizes or uses, so an opening between the kitchen and living room belongs in the permit check.

The wall has to be checked for supports, pipes and wiring before it is changed.

Source: Toronto Building, work that needs a permit

How do plumbing changes and basement use affect approval?

Toronto lists installing or modifying plumbing systems as permit work, while repairing or replacing plumbing fixtures appears on its list of work that does not need a building permit.

Moving a kitchen sink across the room changes the plumbing work that needs to be assessed.

Tell us where the fixtures are now and where you want them to be.

Source: Toronto Building, work that needs a permit

Tell us which rooms are changing

Send the room list, the address and what you want to keep for a written renovation scope.